Chapter 864 Oregon Laws 2001
AN ACT
HB 5029
Relating to state financial
administration; creating new provisions; amending section 3, chapter 909,
Oregon Laws 1999; appropriating money; limiting expenditures; and declaring an
emergency.
Be It Enacted by the People of the State of Oregon:
SECTION 1.
In addition to and not in lieu of any
other appropriation, there is appropriated to the Department of Corrections,
out of the General Fund, for the biennium beginning July 1, 2001, the following
amounts for the acquisition of land and the acquisition, planning,
constructing, altering, repairing, furnishing and equipping of buildings and
facilities:
(1) Central Distribution Center
roof
replacement.................. $1,077,000
(2) Oregon State Penitentiary
groundwater cleanup........... $1,150,000
SECTION 2.
Notwithstanding any other law, the
following amounts are established for the biennium beginning July 1, 2001, as
the maximum limits for the payment of expenses from fees, moneys or other
revenues, including Miscellaneous Receipts, but excluding lottery funds and
federal funds, collected or received by various state agencies for the
acquisition of land and the acquisition, planning, constructing, altering,
repairing, furnishing and equipping of buildings and facilities:
(1) Department of Corrections:
(a) Shutter Creek Correctional
Institution
expansion............ $4,565,571
(b) Lakeview construction......... $27,153,180
(c) Madras construction............ $58,958,287
(d)
Convert Women’s
Correctional Center to a
(e)
men’s facility $1,625,000
(2) Department of Public Safety
Standards and
Training:
Training
Academy planning
and
construction................... $825,000
(3) State Forestry Department:
(a) Tillamook State Forest
Interpretive
Center
design and
construction....... $13,500,000
(b) Tillamook District
headquarters
Admin.
Bldg....................................... $6,500,000
(c) Salem Compound construction
phase III................................ $1,500,000
(4) Department of Transportation:
(a) Lake of the Woods
maintenance
station............. $250,000
(b) Leased facilities acquisition
and
Headquarter Building
improvements....................... $1
(c) Ontario District 14 Office
Building................................. $200,000
(d) Ona Beach Maintenance
Station................................... $250,000
(e) Eugene/Springfield
Maintenance Station............ $300,000
(5) Oregon Department of
Administrative
Services:
(a) Elevator improvements,
phase 2.................................. $1,000,000
(b) Albina Building
improvements....................... $1,121,028
(c) Executive Building HVAC
system
replacement.............. $200,000
(d) Building
Elevator
Replacement Project............ $1,750,000
(e) Commerce Building
renovation............................. $2,887,500
(f) Steam Plant Building
conversion............................. $1,800,000
(g) Planning funds..................... $350,000
(h) Leased facilities
acquisition............................. $1
(i) Space management/
acquisition............................. $1
(j) Building HVAC
improvements....................... $2,536,247
(k) Fish and Wildlife Building
planning
authority............... $1
(L) Department of Environmental
Quality and
Health Lab
planning................................ $1
(m) Salem Area Park and Ride
Station................................... $1
(6) State Fair and Exposition
Center
facilities planning
and
construction................... $10,000,000
(7) Legislative Administration
Capitol wings
and hearing
rooms
planning, equipment
and
renovations.................... $525,000
SECTION 3.
Notwithstanding any other law, the
following amounts are established for the biennium beginning July 1, 2001, as
the maximum limits for payment of expenses from moneys collected or received by
the Oregon Department of Aviation from the Federal Aviation Administration and
from fees, moneys or other revenues, including Miscellaneous Receipts, but
excluding lottery funds, for state-owned airport improvements:
(1) Aurora Airport land appraisals
and land
acquisition................................ $690,000
(2) Condon Airport improvements $563,500
(3) Joseph Airport improvements $509,582
(4) Chiloquin Airport
improvements........................................ $1,447,850
SECTION 4.
Notwithstanding any other law, the
following amounts are established for the biennium beginning July 1, 2001, as
the maximum limits for the expenditure of federal funds collected or received
by various state agencies for the acquisition of land and the acquisition,
planning, constructing, altering, repairing, furnishing and equipping of
buildings and facilities:
(1) Oregon Military Department:
(a) Camp Rilea BOQ addition,
construction..................................... $3,400,000
(b) Camp Rilea BOQ addition,
planning and
design....................... $306,000
(2) State Department of Fish
and Wildlife:
(a) Willamette Falls fishway................ $1,000,000
(b) Resurface Battery A & B
Ponds -
Bonneville.......................... $500,000
(c) Adult holding/acclimation
- Bonneville...................................... $2,600,000
(d) Screening for ESA Fish
at Cascade,
Oxbow,
Bonneville
& Cole Rivers............... $1,000,000
SECTION 5.
The project approvals, appropriations
and expenditure limitations in this 2001 Act expire on June 30, 2007, unless
otherwise noted or changed by the Emergency Board or Legislative Assembly.
SECTION 6.
The expiration date of the project
approvals, appropriations and expenditure limitations authorized by the
Emergency Board or Legislative Assembly for the following projects are extended
to the following dates:
General Other Federal Expiration
Funds Funds Funds Date
(1) Oregon Military
Department:
(a) Camp Rilea
Training and
Simulation
Center $- $7,500 $2,500,000 31-Aug-02
(b) Ontario
Readiness
Center $- $165,275 $330,550 30-Jun-03
(c) Eugene Armed
Forces Reserve
Center $- $901,693 $15,144,710 30-Jun-05
(d) Salem Armed
Forces Reserve
Center $- $227,800 $- 31-Dec-02
(2) Department of
Corrections:
(a) Multnomah Co.
Community
Corrections
Project $- $10,845,000 $- 30-Jun-04
(b) Clatsop Co.
Community
Corrections
Project $- $673,260 $- 30-Jun-04
(3) Oregon
Department of
Administrative
Services:
(a) Chiller
Upgrades
Phase 1 $- $750,000 $- 30-Jun-03
(b) ADA
Improvements
Phase 2 $- $750,000 $- 30-Jun-03
(c) Agriculture
Building
Improvements $- $9,083,467 $- 30-Jun-03
(d) Seismic
Upgrades
Phase 1 $- $1,500,000 $- 30-Jun-03
(e) Key Card
Access
Phase 2 $- $554,122 $- 30-Jun-03
(f) Emergency
Response
(g) North Mall
Redevelopment $- $429,653 $- 30-Jun-03
SECTION 7.
Section 3, chapter 909, Oregon Laws 1999, is amended to read:
Sec. 3.
Notwithstanding any other law, the following amounts are established for the
biennium beginning July 1, 1999, as the maximum limits for the payment of
expenses from fees, moneys or other revenues, including Miscellaneous Receipts,
but excluding lottery funds and federal funds, collected or received by various
state agencies for the acquisition of land and the acquisition, planning,
constructing, altering, repairing, furnishing and equipping of buildings and
facilities:
(1) Employment
Department
purchase Eugene
Field Office................................ $2,500,000
(2) Oregon
Military Department
(a) Armed Forces
Reserve
Center-Salem.............................. $1
(b) Readiness
Center-Ontario.......... $1
(c) Readiness
Center-The Dalles..... $1
(d) Site
improvement,
phase I-Clackamas...................... $1
(e) Consolidated
storage
facility-Clackamas...................... $1
(f) Site
improvement,
phase I-Warrenton...................... $1
(g) Consolidated
storage
facility-Warrenton...................... $1
(3) Department of
Corrections
(a) Expansion
design South
Fork Forest Camp, Powder
River Correctional
Institution, Shutter
Creek Correctional
Institution................................... $750,000
(b) South Fork
Forest
50 bed expansion........................ $2,112,522
(c) South Fork
Forest
electrical upgrade....................... $500,000
(d) Powder River
Correctional
Institution 100
bed expansion............................. $4,949,012
[(e) Lakeview preconstruction........... $1,303,500]
[(f) Junction City preconstruction..... $280,500]
[(g) Madras preconstruction.............. $4,230,600]
[(h) White City preconstruction......... $249,700]
[(i) Groundwater projects................. $850,000]
[(j) Oregon State Correctional
Institution
electrical upgrade
phase II....................................... $983,500]
(e) New facility preconstruction.... $6,064,300
(f) Groundwater projects.............. $850,000
(g) Oregon State Correctional
Institution
electrical upgrade
phase II...................................... $983,500
(4) State
Forestry Department
(a) Salem
Compound construction,
phase II....................................... $11,703,238
(b) Tillamook
State Forest
Interpretive Center design.......... $250,000
(c) Tillamook
District Headquarters
Administrative Building design. $300,000
(d) Forest Grove
District Headquarters
Headquarters site master plan.... $50,000
(5) Department of
Transportation
(a) Hermiston
project....................... $1
(b) Maintenance
Station-Sylvan...... $1
(c) Maintenance
Station-
Government Camp..................... $1,000,000
(d) Maintenance
Station-Lake
of the Woods.............................. $1
(e) Maintenance
Station-Baker City $1
(f) New toilet
buildings-Santiam
Safety Rest Area........................ $1
(g) Maintenance
Station-East
Portland...................................... $1
(h) Design for
2001-2003 projects... $1
(6) Oregon State
Fair and
Exposition Center
(a) Fairgrounds
modernization
master plan................................. $450,000
(b) Fairgrounds
restoration
projects....................................... $1,550,000
(7) Oregon
Department of
Administrative Services
(a) Steam plant
decentralization,
phase II....................................... $680,865
(b) Elevator
improvements,
phase I........................................ $600,000
(c) Labor and
Industries
Building electrical and
HVAC improvements................ $761,729
(d) General
Services Building
electrical and HVAC
improvements............................. $953,726
(e) Planning
funds........................... $125,000
(f) Executive
Building
electrical and HVAC planning... $100,000
(g) Justice
Building planning........... $125,000
(h) Commerce
Building
renovation planning.................... $250,000
(i) Bend
Regional Center
planning...................................... $200,000
(j) Eugene
DMV/Office planning... $125,000
(k) North Mall
Historic District....... $1,000,000
(L) Maintenance
Building
conversion planning.................... $25,000
(m) Salem Motor
Pool
expansion, phase II..................... $450,000
(n) Bend Motor
Pool planning......... $50,000
(o) Capitol Mall
parking
structure planning....................... $150,000
(p) Portland
State Office
Building expansion planning...... $300,000
(q) Eugene
Regional Center planning $500,000
(r) Leased
facilities acquisition....... $1
(s) Space
management/acquisition... $1
(8) Oregon Youth
Authority
MacLaren administration
building design........................... $134,700
SECTION 8.
Notwithstanding any other law, all
sections of this 2001 Act are subject to Oregon Department of Administrative
Services rules related to allotting, controlling, and encumbering funds.
SECTION 9.
This 2001 Act being necessary for the
immediate preservation of the public peace, health and safety, an emergency is
declared to exist, and this 2001 Act takes effect July 1, 2001.
Approved by the Governor
July 27, 2001
Filed in the office of
Secretary of State July 27, 2001
Effective date July 27, 2001
__________