71st OREGON LEGISLATIVE ASSEMBLY--2001 Regular Session
SA to SB 530
LC 1484/SB 530-1
SENATE AMENDMENTS TO
SENATE BILL 530
By COMMITTEE ON BUSINESS, LABOR, AND ECONOMIC DEVELOPMENT
April 11
On page 1 of the printed bill, delete lines 4 through 31 and
delete page 2 and insert:
' { + SECTION 1. + } ORS 455.467 is amended to read:
' 455.467. (1) Except as provided in subsection (2) of this
section, for specialty code plan reviews of simple one and two
family dwellings, the Department of Consumer and Business
Services or a municipality that administers a building inspection
program under ORS 455.150 shall approve or disapprove the
specialty code building plan:
' (a) For a jurisdiction with a population that is less than
300,000, within 10 business days of receiving a complete
application, or shall implement the process described in ORS
455.465.
' (b) For a jurisdiction with a population that is 300,000 or
more, within 15 business days of receiving a complete
application, or shall implement the process described in ORS
455.465.
' (2) The 10-day and 15-day requirements in subsection (1) of
this section do not apply if:
' (a) The plan requires approval by federal, state or local
agencies outside the jurisdiction of the issuing agency;
' (b) The plan is for a complex structure that requires
additional review as determined by the department or
municipality; or
' (c) Based on conditions that exist in the affected
municipality, the Director of the Department of Consumer and
Business Services authorizes a different plan review schedule as
described in a building inspection program submitted under ORS
455.150.
' (3) For specialty code plan reviews of commercial structures,
a municipality shall include in its building inspection program
submitted under ORS 455.150 a process for plan review services.
The municipality shall include in its program detailed reasons
supporting the proposed plan review process. { + The plan review
services provided by the municipality shall:
' (a) Allow an applicant to defer the submittal of plans for
one or more construction phases for a commercial construction
project in accordance with the state building code; and
' (b) Allow an applicant to receive permits for each of the
phases of a commercial construction project as described in the
state building code when the plan review for that phase is
completed.
' (4) For a phased commercial construction project as described
in subsection (3) of this section, the municipality shall inform
the applicant of the detailed plans necessary for each phase of
the project and the estimated time for initial and phased review
of the building plans for conformance with the state building
code.
' (5) An applicant submitting plans under subsection (3) of
this section is responsible for ensuring that the project meets
all specialty code requirements and that the project does not
proceed beyond the level of approval authorized by the building
official. + }
' { - (4) - } { + (6) + } A municipality that repeatedly
fails to meet the plan review period described in this section or
otherwise authorized in its building inspection program submitted
under ORS 455.150 shall be considered to be engaging in a pattern
of conduct of failing to provide timely plan reviews under ORS
455.160.'.
----------