SECTION 1. For the purpose of carrying out the provisions of ORS 291.055 (1)(e), the following fees for the Air Quality and Water Quality Divisions, modified by the Department of Environmental Quality by rule and approved by the Oregon Department of Administrative Services, are approved:
______________________________________________________________________________
(1) Air Quality Division:
(a) Air Contaminant
Discharge Permits.............. Air contaminant
discharge permits
and
associated fee
schedule
table 2
- OAR 340-216-0020
(A) Basic Air Contaminant
Discharge
Permit........................ $ 300
(B) General Air Contaminant
Discharge
Permit,
Fee
Class One............................. $ 600
(C) General Air Contaminant
Discharge
Permit,
Fee
Class Two............................. $ 1,080
(D) General Air Contaminant
Discharge
Permit,
Fee
Class Three.......................... $ 1,560
(E) Simple Low Fee Air Contaminant
Discharge
Permit........................ $ 1,600
(F) Simple High Fee Air Contaminant
Discharge
Permit........................ $ 3,200
(G) Standard Air Contaminant
Discharge
Permit........................ $ 6,400
(H) Late fee, 8 to 30
days
late, as percent
of
annual fee................................ 5 percent
(I) Late fee, 31 to 60
days late, as percent
of
annual fee................................ 10 percent
(J) Late fee, 61 days
or
more late, as percent
of
annual fee................................ 20 percent
(b) Automobile Franchise Dealers
On-Site
Vehicle Emissions
Test
Certificates:
(A) Portland Vehicle
Inspection
Area........................... $ 26
(B) Medford-Ashland Air
Quality
Maintenance
Area............................................. $ 26
(2) Water Quality Division -
Wastewater
Permit Fees:
(a) Water Quality Permits,
New
Application Fees:
(A) Major Industries......................... $ 37,680
(B) Minor Industries and
Agricultural................................. $ 7,535
(C) Major Domestic.......................... $ 24,000
(D) Minor Domestic Da, Db............. $ 4,800
(E) Minor Domestic E...................... $ 2,400
(F) Minor Domestic F....................... $ 600
(G) Water Pollution Control
Facilities
permits for on-site
sewage
disposal systems
for
greater than
1,200
gallons per day.................. $ 2,400
(H) Water Pollution Control
Facilities
permits for on-site
sewage
disposal systems
for
less than or equal to
1,200
gallons per day.................. $ 480
(I) Water Pollution Control
Facilities
on-site sewage
General
Permit............................ $ 180
(J) General Permits 100, 200,
400,
500, 600 (over 1,500 cubic
yards
per year), 900, 1000
and
1400A................................... $ 95
(K) General Permits 300, 1300,
1400B,
1500 and 1600................ $ 185
(L) General Permits all other
1200
and 1700............................. $ 280
(M) General Permits not
elsewhere
specified..................... $ 280
(b) Water Quality Permits,
Renewal
or Permit
Modification
Fees With
Request
For Effluent Limit
Modification:
(A) Major Industries......................... $ 18,840
(B) Minor Industries and
Agricultural................................. $ 3,765
(C) Major Domestic.......................... $ 12,000
(D) Minor Domestic Da, Db............. $ 2,400
(E) Minor Domestic E...................... $ 1,200
(F) Water Pollution Control
Facilities
for on-site sewage
systems
for greater than 1,200
gallons
per day............................ $ 1,200
(G) Water Pollution Control
Facilities
for on-site sewage
systems
for less than or equal
to
1,200 gallons per day
(permit
renewal).......................... $ 240
(H) Water Pollution Control
Facilities
for on-site sewage
systems
for less than or equal
to
1,200 gallons per day
(permit
modification only)........... $ 180
(c) Water Quality Permits,
Renewal
Fees Without Effluent
Limit
Modification:
(A) Major Industries......................... $ 9,420
(B) Minor Industries and
Agricultural................................. $ 1,415
(C) Major Domestic.......................... $ 6,000
(D) Minor Domestic Da, Db............. $ 900
(E) Minor Domestic E...................... $ 600
(F) Minor Domestic F....................... $ 240
(G) Water Pollution Control
Facilities
for on-site sewage
systems
for greater than 1,200
gallons
per day............................ $ 600
(H) Water Pollution Control
Facilities
for on-site sewage
systems
for less than or equal
to
1,200 gallons per day.............. $ 120
(d) Miscellaneous Permit Fees:
(A) Filing Fee, excluding general
permit
600 processing less
than
five cubic yards per
day
and general permit 700
with
intake hose diameter of
four
inches or less....................... $ 60
(B) Permit Modification not
involving
an increase in
effluent
limits, excluding
Water
Pollution Control
Facilities
permits for
on-site
sewage systems.............. $ 600
(C) Water Pollution Control
Facilities
permits for on-site
sewage
systems greater than
1,200
gallons per day,
modification
without increase
in
effluent limits.......................... $ 600
(D) Water Pollution Control
Facilities
permits for on-site
sewage
systems less than or
equal
to 1,200 gallons per day,
modification
without increase
in
effluent limits.......................... $ 120
(E) Special Water Pollution
Control
Facilities Permits........... $ 300
(F) Renewal Fee for General
Permits,
excluding general
permits
600, if for less than
five
cubic yards per day, or
if
for more than five cubic yards
per
day but less than 1,500 cubic
yards
per year, and 700.............. $ 40
(G) Modification of septage
alkaline
stabilization facility
permits......................................... $ 240
(H) Disposal system plan review
for
general permits, excluding
Water
Pollution Control
Facilities
permits for on-site
sewage
systems.......................... $ 375
(I) Site inspection and
evaluation
for general permits,
excluding
Water Pollution
Control
Facilities permits for
on-site
sewage systems.............. $ 940
(J) Technical activities fee:
New
or substantially modified
sewage
treatment facility........... $ 5,520
(K) Technical activities fee:
Minor
sewage treatment
facility
modifications
and
pump stations....................... $ 600
(L) Technical activities fee:
Pressure
sewer system
or
major sewer collection
system
expansion........................ $ 420
(M) Technical activities fee:
Minor
sewer collection
system
expansion or
modification................................. $ 120
(N) Technical activities fee:
New
or substantially modified
Water
Pollution Control
Facilities
utilizing alkaline
agents
to stabilize septage......... $ 600
(e) Site Evaluation and Plan
Review
Fees for Water Pollution
Control
Facilities permits
for
on-site sewage disposal
systems:
(A) Water Pollution Control
Facilities
site evaluation fee
for
facilities greater than
5,000
gallons per day.................. $ 1,440
(B) Water Pollution Control
Facilities
site evaluation
confirmation
fee.......................... $ 420
(C) Water Pollution Control
Facilities
plan review fee for
commercial
facilities greater
than
or equal to 5,000
gallons
per day............................ $ 600
(D) Water Pollution Control
Facilities
plan review for non-
commercial
facilities................... $ 120
(f) Annual Compliance Determination
Fees:
(A) Pulp, paper and other fiber
pulping
industry........................... $ 11,300
(B) Sugar beet, potato and other
produce
processing..................... $ 11,300
(C) Seafood processing: bottom
fish,
crab or oyster...................... $ 1,270
(D) Seafood processing: shrimp....... $ 1,270
(E) Seafood processing: salmon
or
tuna......................................... $ 2,260
(F) Seafood processing: surimi........ $ 2,260
(G) Electroplating: Rectifier
output
capacity 15,000 amps
or
more........................................ $ 11,300
(H) Electroplating: Rectifier
output
capacity less than
15,000
amps but more than
5,000
amps.................................. $ 5,650
(I) Primary aluminum smelting........ $ 11,300
(J) Primary smelting or refining
of
nonferrous metals using sand
chlorination
separation
facility.......................................... $ 11,300
(K) Primary smelting or refining
of
ferrous and nonferrous
metals
not otherwise
classified...................................... $ 5,650
(L) Alkalies, chlorine, pesticide
or
fertilizer manufacturing
with
discharge of process
wastewater.................................. $ 11,300
(M) Petroleum refineries with a
capacity
greater than 15,000
barrels
per day discharging
process
wastewater..................... $ 11,300
(N) Cooling water discharges in excess
of
20,000 BTU per second.......... $ 5,650
(O) Milk products processing
industry
processing in excess
of
250,000 pounds of milk
per
day......................................... $ 11,300
(P) Major mining operations............ $ 11,300
(Q) Minor mining operations:
Medium,
using mechanical
processing................................... $ 3,765
(R) Minor mining operations:
Medium,
using froth
flotation....................................... $ 5,650
(S) Minor mining operations:
Medium,
using chemical
leaching....................................... $ 7,535
(T) Minor mining operations:
Small,
using mechanical
processing................................... $ 940
(U) Minor mining operations:
Small,
using froth
flotation....................................... $ 1,880
(V) Minor mining operations:
Small,
using chemical
leaching....................................... $ 3,765
(W) All facilities not otherwise
classified
that dispose
of
process wastewater................ $ 2,260
(X) All facilities not otherwise
classified
that dispose of
nonprocess
wastewater............... $ 1,415
(Y) Dairies and other confined
feeding
operations on
individual
permits........................ $ 845
(Z) All facilities that dispose
of
wastewater only by
evaporation
from watertight
ponds
or basins........................... $ 845
(AA) Sewage disposal of 50
million
gallons per day
or
more ....................................... $ 50,890
(BB) Sewage disposal of at
least
25 million gallons
but
less than 50 million
gallons
per day............................ $ 29,410
(CC) Sewage disposal of at
least
10 million gallons
but
less than 25 million
gallons
per day............................ $ 13,220
(DD) Sewage disposal of at
least
5 million gallons
but
less than 10 million
gallons
per day............................ $ 8,040
(EE) Sewage disposal of at
least
5 million gallons
but
less than 10 million
gallons
per day for treatment
in
lagoons that discharge
into
surface waters...................... $ 3,680
(FF) Sewage disposal of at
least
2 million gallons
but
less than 5 million
gallons
per day............................ $ 5,010
(GG) Sewage disposal of at
least
2 million gallons
but
less than 5 million
gallons
per day for treatment
in
lagoons that discharge into
surface
waters............................. $ 2,190
(HH) Sewage disposal of at
least
1 million gallons but
less
than 2 million gallons
per
day......................................... $ 3,010
(II) Sewage disposal of at
least
1 million gallons but
less
than 2 million gallons
per
day for treatment in
lagoons
that discharge into
surface
waters............................. $ 1,270
(JJ) Sewage disposal of less
than
1 million gallons
per
day and not otherwise
categorized
under
Category
E.................................. $ 1,145
(KK) Sewage disposal of less
than
1 million gallons
per
day for treatment in
lagoons
that discharge into
surface
waters and not
otherwise
categorized under
Category
E.................................. $ 750
(LL) Sewage disposal where
treatment
is limited to
lagoons
that do not discharge
into
surface waters...................... $ 720
(MM) Septage alkaline stabilization
facilities....................................... $ 240
(NN) Pretreatment base fee................ $ 1,200
(OO) Pretreatment base fee
per
significant industrial user..... $ 400
(PP) Population-based fee rate
factor........................................... 0.09645
(QQ) On-site sewage lagoon
with
no discharge........................ $ 720
(RR) Standard or alternative
subsurface
system not otherwise
listed
with design flow of
20,000
gallons per day or
more............................................. $ 600
(SS) Standard or alternative
subsurface
system not otherwise
listed
with design flow less
than
20,000 gallons per day........ $ 300
(TT) Aerobic on-site sewage system,
1,500
gallons per day or more.... $ 600
(UU) Aerobic on-site sewage system,
less
than 1,500 gallons per day.. $ 300
(VV) Recirculating gravel filter,
1,500
gallons per day or more.... $ 600
(WW) Recirculating gravel filter,
less
than 1,500 gallons per
day............................................... $ 300
(XX) Sand filter, 1,500
gallons
per day or more.............. $ 600
(YY) Sand filter, less than
1,500
gallons per day.................. $ 300
(ZZ) On-site sewage holding tanks.... $ 240
(AAA) NPDES General Permit 100
Cooling
water/heat pumps.......... $ 330
(BBB) NPDES General Permit 200
Filter
backwash........................... $ 330
(CCC) NPDES General Permit 300
Fish
hatcheries............................ $ 330
(DDD) NPDES General Permit 400
Log
ponds.................................... $ 330
(EEE) NPDES General Permit 500
Boiler
blowdown.......................... $ 330
(FFF) NPDES General Permit 900
Seafood
processing..................... $ 330
(GGG) NPDES General Permit 1000
Gravel
mining.............................. $ 330
(HHH) NPDES General Permit 1200A
Storm
water: sand, gravel
and
other nonmetallic mining..... $ 330
(III) NPDES General Permit 1200C
Storm
water: construction
activities
of 5 acres or more....... $ 330
(JJJ) NPDES General Permit 1200CA
Storm
water: municipal
construction
activities of 5
acres
or more.............................. $ 330
(KKK) NPDES General Permit 1200Z
Storm
water: all other
industrial...................................... $ 330
(LLL) NPDES General Permit 1300
Oily
storm water runoff.............. $ 330
(MMM) WPCF General Permit 1400A
Seasonal
wineries; crop
preparation
for market;
fresh
pack produce..................... $ 185
(NNN) WPCF General Permit 1400B
Canneries;
processed foods;
meat
processing and packing;
poultry,
marine and other
animal
products processing;
oils
and extracts.......................... $ 330
(OOO) NPDES General Permit 1500A
and
WPCF General Permit 1500B
Petroleum
hydrocarbon
cleanup........................................ $ 330
(PPP) WPCF General Permit 1600
Small
froth flotation
mineral
extraction....................... $ 330
(QQQ) NPDES General Permit 1700A
and
WPCF General Permit 1700B
Vehicle
and equipment
wash
water................................... $ 330
(RRR) NPDES General Permit 1900
Noncontact
geothermal
heat
exchange............................. $ 330
(SSS) NPDES General Permit 1200
COLS
Storm water: Columbia
Slough
Watershed....................... $ 330
(3) Water Quality Division -
Operator
Certification Fees
and
Annual Program
Support
Fees:
(a) Schedule A, Operator
Certification
Fees:
(A) Application fee, new certificate:
(i) Grade I or Grade I
provisional;
treatment or
collection..................................... $ 50
(ii) Grade I or Grade I
provisional;
treatment and
collection..................................... $ 50
(iii) Grade II; treatment
or
collection................................. $ 70
(iv) Grade III; treatment
or
collection................................. $ 90
(v) Grade IV; treatment
or
collection................................. $ 110
(B) Examination, reexamination
or
rescheduled exam fee:
(i) Grade I or Grade I
provisional;
treatment or
collection..................................... $ 50
(ii) Grade I or Grade I
provisional;
treatment and
collection
.................................... $ 100
(iii) Grade II treatment or
collection
.................................... $ 50
(iv) Grade III treatment
or
collection................................. $ 50
(v) Grade IV treatment
or
collection................................. $ 50
(C) Two-year certificate
renewal
fee:
(i) Grade I or Grade II.................... $ 100
(ii) Grade III or Grade IV................ $ 100
(iii) Combined Grade I or Grade II.. $ 100
(iv) Combined Grade I or Grade II
and
Grade III or Grade IV......... $ 100
(v) Combined Grade III or Grade IV $ 100
(D) Certificate by reciprocity
application
fee:
(i) Grade I or Grade I
provisional;
treatment
or
collection................................. $ 100
(ii) Grade I or Grade I
provisional;
treatment
and
collection.............................. $ 150
(iii) Grade II treatment
or
collection................................. $ 120
(iv) Grade III treatment
or
collection................................. $ 140
(v) Grade IV treatment
or
collection................................. $ 160
(E) Other certification fees:
(i) Open schedule examination....... $ 100
(ii) Post-examination application..... $ 30
(iii) Certificate reinstatement fee,
one
or two certificates................ $ 75
(iv) Certificate and renewal
document
replacement fee......... $ 30
(b) Schedule B, Annual Operator
Certification
Program
Support
Fees:
(A) Group A, less than
0.075
million gallons
per
day......................................... $ 50
(B) Group B, 0.075 to 0.499
million
gallons per day................ $ 60
(C) Group C, 0.500 to 0.999
million
gallons per day................ $ 120
(D) Group D, 1.0 to 1.999
million
gallons per day................ $ 225
(E) Group E, 2.0 to 4.999
million
gallons per day................ $ 525
(F) Group F, 5.0 to 9.999
million
gallons per day................ $ 1,150
(G) Group G, 10.0 to 19.999
million
gallons per day................ $ 2,250
(H) Group H, 20.0 to 29.999
million
gallons per day................ $ 3,750
(I) Group I, 30.0 to 39.999
million
gallons per day................ $ 5,250
(J) Group J, 40.0 to 59.999
million
gallons per day................ $ 7,500
(K) Group K, 60.0 to 79.999
million
gallons per day................ $ 10,500
(L) Group L, 80.0 to 119.999
million
gallons per day................ $ 15,000
(M) Group M, 120 million
gallons
per day or more.............. $ 21,000
(N) Late fee of $50 or 10
percent
of the annual fee,
whichever is greater.
______________________________________________________________________________
SECTION 2. This 2003 Act being necessary for the immediate preservation of the public peace, health and safety, an emergency is declared to exist, and this 2003 Act takes effect July 1, 2003.
Approved by the Governor August 21, 2003
Filed in the office of Secretary of State August 21, 2003
Effective date August 21, 2003
__________