          SECTION 1. For the purpose of carrying out the provisions of ORS 291.055 (1)(e), the following fees for the Air Quality and Water Quality Divisions, modified by the Department of Environmental Quality by rule and approved by the Oregon Department of Administrative Services, are approved:

______________________________________________________________________________

 

     (1)       Air Quality Division:

     (a)       Air Contaminant

                Discharge Permits..............       Air contaminant

                                                                    discharge permits

                                                                    and associated fee

                                                                    schedule table 2

                                                                    - OAR 340-216-0020

     (A)      Basic Air Contaminant

                Discharge Permit........................       $                    300

     (B)      General Air Contaminant

                Discharge Permit,

                Fee Class One.............................       $                    600

     (C)      General Air Contaminant

                Discharge Permit,

                Fee Class Two.............................       $                 1,080

     (D)      General Air Contaminant

                Discharge Permit,

                Fee Class Three..........................       $                 1,560

     (E)       Simple Low Fee Air Contaminant

                Discharge Permit........................       $                 1,600

     (F)       Simple High Fee Air Contaminant

                Discharge Permit........................       $                 3,200

     (G)      Standard Air Contaminant

                Discharge Permit........................       $                 6,400

     (H)      Late fee, 8 to 30

                days late, as percent

                of annual fee................................                    5 percent

     (I)        Late fee, 31 to 60

                 days late, as percent

                of annual fee................................                  10 percent

     (J)       Late fee, 61 days

                or more late, as percent

                of annual fee................................                  20 percent

     (b)       Automobile Franchise Dealers

                On-Site Vehicle Emissions

                Test Certificates:

     (A)      Portland Vehicle

                Inspection Area...........................       $                      26

     (B)      Medford-Ashland Air

                Quality Maintenance

                Area.............................................       $                      26

     (2)       Water Quality Division -

                Wastewater Permit Fees:

     (a)       Water Quality Permits,

                New Application Fees:

     (A)      Major Industries.........................       $               37,680

     (B)      Minor Industries and

                Agricultural.................................       $                 7,535

     (C)      Major Domestic..........................       $               24,000

     (D)      Minor Domestic Da, Db.............       $                 4,800

     (E)       Minor Domestic E......................       $                 2,400

     (F)       Minor Domestic F.......................       $                    600

     (G)      Water Pollution Control

                Facilities permits for on-site

                sewage disposal systems

                for greater than

                1,200 gallons per day..................       $                 2,400

     (H)      Water Pollution Control

                Facilities permits for on-site

                sewage disposal systems

                for less than or equal to

                1,200 gallons per day..................       $                    480

     (I)        Water Pollution Control

                Facilities on-site sewage

                General Permit............................       $                    180

     (J)       General Permits 100, 200,

                400, 500, 600 (over 1,500 cubic

                yards per year), 900, 1000

                and 1400A...................................       $                      95

     (K)      General Permits 300, 1300,

                1400B, 1500 and 1600................       $                    185

     (L)       General Permits all other

                1200 and 1700.............................       $                    280

     (M)     General Permits not

                elsewhere specified.....................       $                    280

     (b)       Water Quality Permits,

                Renewal or Permit

                Modification Fees With

                Request For Effluent Limit

                Modification:

     (A)      Major Industries.........................       $               18,840

     (B)      Minor Industries and

                Agricultural.................................       $                 3,765

     (C)      Major Domestic..........................       $               12,000

     (D)      Minor Domestic Da, Db.............       $                 2,400

     (E)       Minor Domestic E......................       $                 1,200

     (F)       Water Pollution Control

                Facilities for on-site sewage

                systems for greater than 1,200

                gallons per day............................       $                 1,200

     (G)      Water Pollution Control

                Facilities for on-site sewage

                systems for less than or equal

                to 1,200 gallons per day

                (permit renewal)..........................       $                    240

     (H)      Water Pollution Control

                Facilities for on-site sewage

                systems for less than or equal

                to 1,200 gallons per day

                (permit modification only)...........       $                    180

     (c)       Water Quality Permits,

                Renewal Fees Without Effluent

                Limit Modification:

     (A)      Major Industries.........................       $                 9,420

     (B)      Minor Industries and

                Agricultural.................................       $                 1,415

     (C)      Major Domestic..........................       $                 6,000

     (D)      Minor Domestic Da, Db.............       $                    900

     (E)       Minor Domestic E......................       $                    600

     (F)       Minor Domestic F.......................       $                    240

     (G)      Water Pollution Control

                Facilities for on-site sewage

                systems for greater than 1,200

                gallons per day............................       $                    600

     (H)      Water Pollution Control

                Facilities for on-site sewage

                systems for less than or equal

                to 1,200 gallons per day..............       $                    120

     (d)       Miscellaneous Permit Fees:

     (A)      Filing Fee, excluding general

                permit 600 processing less

                than five cubic yards per

                day and general permit 700

                with intake hose diameter of

                four inches or less.......................       $                      60

     (B)      Permit Modification not

                involving an increase in

                effluent limits, excluding

                Water Pollution Control

                Facilities permits for

                on-site sewage systems..............       $                    600

     (C)      Water Pollution Control

                Facilities permits for on-site

                sewage systems greater than

                1,200 gallons per day,

                modification without increase

                in effluent limits..........................       $                    600

     (D)      Water Pollution Control

                Facilities permits for on-site

                sewage systems less than or

                equal to 1,200 gallons per day,

                modification without increase

                in effluent limits..........................       $                    120

     (E)       Special Water Pollution

                Control Facilities Permits...........       $                    300

     (F)       Renewal Fee for General

                Permits, excluding general

                permits 600, if for less than

                five cubic yards per day, or

                if for more than five cubic yards

                per day but less than 1,500 cubic

                yards per year, and 700..............       $                      40

     (G)      Modification of septage

                alkaline stabilization facility

                permits.........................................       $                    240

     (H)      Disposal system plan review

                for general permits, excluding

                Water Pollution Control

                Facilities permits for on-site

                sewage systems..........................       $                    375

     (I)        Site inspection and

                evaluation for general permits,

                excluding Water Pollution

                Control Facilities permits for

                on-site sewage systems..............       $                    940

     (J)       Technical activities fee:

                New or substantially modified

                sewage treatment facility...........       $                 5,520

     (K)      Technical activities fee:

                Minor sewage treatment

                facility modifications

                and pump stations.......................       $                    600

     (L)       Technical activities fee:

                Pressure sewer system

                or major sewer collection

                system expansion........................       $                    420

     (M)     Technical activities fee:

                Minor sewer collection

                system expansion or

                modification.................................       $                    120

     (N)      Technical activities fee:

                New or substantially modified

                Water Pollution Control

                Facilities utilizing alkaline

                agents to stabilize septage.........       $                    600

     (e)       Site Evaluation and Plan

                Review Fees for Water Pollution

                Control Facilities permits

                for on-site sewage disposal

                systems:

     (A)      Water Pollution Control

                Facilities site evaluation fee

                for facilities greater than

                5,000 gallons per day..................       $                 1,440

     (B)      Water Pollution Control

                Facilities site evaluation

                confirmation fee..........................       $                    420

     (C)      Water Pollution Control

                Facilities plan review fee for

                commercial facilities greater

                than or equal to 5,000

                gallons per day............................       $                    600

     (D)      Water Pollution Control

                Facilities plan review for non-

                commercial facilities...................       $                    120

     (f)        Annual Compliance Determination

                Fees:

     (A)      Pulp, paper and other fiber

                pulping industry...........................       $               11,300

     (B)      Sugar beet, potato and other

                produce processing.....................       $               11,300

     (C)      Seafood processing: bottom

                fish, crab or oyster......................       $                 1,270

     (D)      Seafood processing: shrimp.......       $                 1,270

     (E)       Seafood processing: salmon

                or tuna.........................................       $                 2,260

     (F)       Seafood processing: surimi........       $                 2,260

     (G)      Electroplating: Rectifier

                output capacity 15,000 amps

                or more........................................       $               11,300

     (H)      Electroplating: Rectifier

                output capacity less than

                15,000 amps but more than

                5,000 amps..................................       $                 5,650

     (I)        Primary aluminum smelting........       $               11,300

     (J)       Primary smelting or refining

                of nonferrous metals using sand

                chlorination separation

                facility..........................................       $               11,300

     (K)      Primary smelting or refining

                of ferrous and nonferrous

                metals not otherwise

                classified......................................       $                 5,650

     (L)       Alkalies, chlorine, pesticide

                or fertilizer manufacturing

                with discharge of process

                wastewater..................................       $               11,300

     (M)     Petroleum refineries with a

                capacity greater than 15,000

                barrels per day discharging

                process wastewater.....................       $               11,300

     (N)      Cooling water discharges in excess

                of 20,000 BTU per second..........       $                 5,650

     (O)      Milk products processing

                industry processing in excess

                of 250,000 pounds of milk

                per day.........................................       $               11,300

     (P)       Major mining operations............       $               11,300

     (Q)      Minor mining operations:

                Medium, using mechanical

                processing...................................       $                 3,765

     (R)      Minor mining operations:

                Medium, using froth

                flotation.......................................       $                 5,650

     (S)       Minor mining operations:

                Medium, using chemical

                leaching.......................................       $                 7,535

     (T)       Minor mining operations:

                Small, using mechanical

                processing...................................       $                    940

     (U)      Minor mining operations:

                Small, using froth

                flotation.......................................       $                 1,880

     (V)      Minor mining operations:

                Small, using chemical

                leaching.......................................       $                 3,765

     (W)     All facilities not otherwise

                classified that dispose

                of process wastewater................       $                 2,260

     (X)      All facilities not otherwise

                classified that dispose of

                nonprocess wastewater...............       $                 1,415

     (Y)       Dairies and other confined

                feeding operations on

                individual permits........................       $                    845

     (Z)       All facilities that dispose

                of wastewater only by

                evaporation from watertight

                ponds or basins...........................       $                    845

     (AA)    Sewage disposal of 50

                million gallons per day

                or more .......................................       $               50,890

     (BB)    Sewage disposal of at

                least 25 million gallons

                but less than 50 million

                gallons per day............................       $               29,410

     (CC)    Sewage disposal of at

                least 10 million gallons

                but less than 25 million

                gallons per day............................       $               13,220

     (DD)   Sewage disposal of at

                least 5 million gallons

                but less than 10 million

                gallons per day............................       $                 8,040

     (EE)    Sewage disposal of at

                least 5 million gallons

                but less than 10 million

                gallons per day for treatment

                in lagoons that discharge

                into surface waters......................       $                 3,680

     (FF)     Sewage disposal of at

                least 2 million gallons

                but less than 5 million

                gallons per day............................       $                 5,010

     (GG)   Sewage disposal of at

                least 2 million gallons

                but less than 5 million

                gallons per day for treatment

                in lagoons that discharge into

                surface waters.............................       $                 2,190

     (HH)   Sewage disposal of at

                least 1 million gallons but

                less than 2 million gallons

                per day.........................................       $                 3,010

     (II)      Sewage disposal of at

                least 1 million gallons but

                less than 2 million gallons

                per day for treatment in

                lagoons that discharge into

                surface waters.............................       $                 1,270

     (JJ)     Sewage disposal of less

                than 1 million gallons

                per day and not otherwise

                categorized under

                Category E..................................       $                 1,145

     (KK)   Sewage disposal of less

                than 1 million gallons

                per day for treatment in

                lagoons that discharge into

                surface waters and not

                otherwise categorized under

                Category E..................................       $                    750

     (LL)    Sewage disposal where

                treatment is limited to

                lagoons that do not discharge

                into surface waters......................       $                    720

     (MM) Septage alkaline stabilization

                facilities.......................................       $                    240

     (NN)   Pretreatment base fee................       $                 1,200

     (OO)   Pretreatment base fee

                per significant industrial user.....       $                    400

     (PP)     Population-based fee rate

                factor...........................................                      0.09645

     (QQ)   On-site sewage lagoon

                with no discharge........................       $                    720

     (RR)   Standard or alternative

                subsurface system not otherwise

                listed with design flow of

                20,000 gallons per day or

                more.............................................       $                    600

     (SS)     Standard or alternative

                subsurface system not otherwise

                listed with design flow less

                than 20,000 gallons per day........       $                    300

     (TT)    Aerobic on-site sewage system,

                1,500 gallons per day or more....       $                    600

     (UU)    Aerobic on-site sewage system,

                less than 1,500 gallons per day..       $                    300

     (VV)    Recirculating gravel filter,

                1,500 gallons per day or more....       $                    600

     (WW)  Recirculating gravel filter,

                less than 1,500 gallons per

                day...............................................       $                    300

     (XX)    Sand filter, 1,500

                gallons per day or more..............       $                    600

     (YY)    Sand filter, less than

                1,500 gallons per day..................       $                    300

     (ZZ)     On-site sewage holding tanks....       $                    240

     (AAA) NPDES General Permit 100

                Cooling water/heat pumps..........       $                    330

     (BBB) NPDES General Permit 200

                Filter backwash...........................       $                    330

     (CCC) NPDES General Permit 300

                Fish hatcheries............................       $                    330

     (DDD)        NPDES General Permit 400

                Log ponds....................................       $                    330

     (EEE)  NPDES General Permit 500

                Boiler blowdown..........................       $                    330

     (FFF)  NPDES General Permit 900

                Seafood processing.....................       $                    330

     (GGG)      NPDES General Permit 1000

                Gravel mining..............................       $                    330

     (HHH)   NPDES General Permit 1200A

                Storm water: sand, gravel

                and other nonmetallic mining.....       $                    330

     (III)     NPDES General Permit 1200C

                Storm water: construction

                activities of 5 acres or more.......       $                    330

     (JJJ)   NPDES General Permit 1200CA

                Storm water: municipal

                construction activities of 5

                acres or more..............................       $                    330

     (KKK)    NPDES General Permit 1200Z

                Storm water: all other

                industrial......................................       $                    330

     (LLL)  NPDES General Permit 1300

                Oily storm water runoff..............       $                    330

     (MMM)  WPCF General Permit 1400A

                Seasonal wineries; crop

                preparation for market;

                fresh pack produce.....................       $                    185

     (NNN)     WPCF General Permit 1400B

                Canneries; processed foods;

                meat processing and packing;

                poultry, marine and other

                animal products processing;

                oils and extracts..........................       $                    330

     (OOO)   NPDES General Permit 1500A

                and WPCF General Permit 1500B

                Petroleum hydrocarbon

                cleanup........................................       $                    330

     (PPP)  WPCF General Permit 1600

                Small froth flotation

                mineral extraction.......................       $                    330

     (QQQ)   NPDES General Permit 1700A

                and WPCF General Permit 1700B

                Vehicle and equipment

                wash water...................................       $                    330

     (RRR)      NPDES General Permit 1900

                Noncontact geothermal

                heat exchange.............................       $                    330

     (SSS)  NPDES General Permit 1200

                COLS Storm water: Columbia

                Slough Watershed.......................       $                    330

     (3)       Water Quality Division -

                Operator Certification Fees

                and Annual Program

                Support Fees:

     (a)       Schedule A, Operator

                Certification Fees:

     (A)      Application fee, new certificate:

     (i)        Grade I or Grade I

                provisional; treatment or

                collection.....................................       $                      50

     (ii)       Grade I or Grade I

                provisional; treatment and

                collection.....................................       $                      50

     (iii)      Grade II; treatment

                or collection.................................       $                      70

     (iv)      Grade III; treatment

                or collection.................................       $                      90

     (v)       Grade IV; treatment

                or collection.................................       $                    110

     (B)      Examination, reexamination

                or rescheduled exam fee:

     (i)        Grade I or Grade I

                provisional; treatment or

                collection.....................................       $                      50

     (ii)       Grade I or Grade I

                provisional; treatment and

                collection ....................................       $                    100

     (iii)      Grade II treatment or

                collection ....................................       $                      50

     (iv)      Grade III treatment

                or collection.................................       $                      50

     (v)       Grade IV treatment

                or collection.................................       $                      50

     (C)      Two-year certificate

                renewal fee:

     (i)        Grade I or Grade II....................       $                    100

     (ii)       Grade III or Grade IV................       $                    100

     (iii)      Combined Grade I or Grade II..       $                    100

     (iv)      Combined Grade I or Grade II

                and Grade III or Grade IV.........       $                    100

     (v)       Combined Grade III or Grade IV     $                    100

     (D)      Certificate by reciprocity

                application fee:

     (i)        Grade I or Grade I

                provisional; treatment

                or collection.................................       $                    100

     (ii)       Grade I or Grade I

                provisional; treatment

                and collection..............................       $                    150

     (iii)      Grade II treatment

                or collection.................................       $                    120

     (iv)      Grade III treatment

                or collection.................................       $                    140

     (v)       Grade IV treatment

                or collection.................................       $                    160

     (E)       Other certification fees:

     (i)        Open schedule examination.......       $                    100

     (ii)       Post-examination application.....       $                      30

     (iii)      Certificate reinstatement fee,

                one or two certificates................       $                      75

     (iv)      Certificate and renewal

                document replacement fee.........       $                      30

     (b)       Schedule B, Annual Operator

                Certification Program

                Support Fees:

     (A)      Group A, less than

                0.075 million gallons

                per day.........................................       $                      50

     (B)      Group B, 0.075 to 0.499

                million gallons per day................       $                      60

     (C)      Group C, 0.500 to 0.999

                million gallons per day................       $                    120

     (D)      Group D, 1.0 to 1.999

                million gallons per day................       $                    225

     (E)       Group E, 2.0 to 4.999

                million gallons per day................       $                    525

     (F)       Group F, 5.0 to 9.999

                million gallons per day................       $                 1,150

     (G)      Group G, 10.0 to 19.999

                million gallons per day................       $                 2,250

     (H)      Group H, 20.0 to 29.999

                million gallons per day................       $                 3,750

     (I)        Group I, 30.0 to 39.999

                million gallons per day................       $                 5,250

     (J)       Group J, 40.0 to 59.999

                million gallons per day................       $                 7,500

     (K)      Group K, 60.0 to 79.999

                million gallons per day................       $               10,500

     (L)       Group L, 80.0 to 119.999

                million gallons per day................       $               15,000

     (M)     Group M, 120 million

                gallons per day or more..............       $               21,000

     (N)      Late fee of $50 or 10

                percent of the annual fee,

                whichever is greater.

 

______________________________________________________________________________

 

          SECTION 2. This 2003 Act being necessary for the immediate preservation of the public peace, health and safety, an emergency is declared to exist, and this 2003 Act takes effect July 1, 2003.

 

Approved by the Governor August 21, 2003

 

Filed in the office of Secretary of State August 21, 2003

 

Effective date August 21, 2003

__________