Chapter 331 Oregon Laws 1999
Session Law
AN ACT
HB 2733
Relating to claims filed
with the Construction Contractors Board; amending ORS 701.145.
Be It Enacted by the People of the State of Oregon:
SECTION 1.
ORS 701.145 is amended to read:
701.145. (1) Any person having a claim against a contractor of
the type referred to in ORS 701.140 may file with the Construction Contractors
Board a statement of the claim in such form as the board prescribes.
(2) The board may refuse to accept, or refuse at any time to
continue processing, a claim if:
(a) The same facts and issues involved in the claim have been
submitted to a court of competent jurisdiction for determination or have been
submitted to any other entity authorized by law or the parties to effect a resolution
and settlement;
(b) The claimant does not permit the contractor against whom
the claim is filed to be present at any inspection made by the board;
(c) The board determines that the contractor against whom the
claim is filed is capable of complying with recommendations made by the board
relative to the claim, but the claimant does not permit the contractor to
comply with the recommendations. However, the board may refuse to accept or
further process a claim under this paragraph only if the contractor was
registered at the time the work was first performed and is registered at the
time the board makes its recommendations;
(d) The board determines that the nature or complexity of the
claim is such that a court is the appropriate forum for the adjudication of the
claim; or
(e) The amount in controversy is less than an amount adopted by
the board and not more than $250.
(3) The board shall not process a claim, including a claim
based upon a court judgment or arbitration award, unless the claim is filed in
a timely manner as follows:
(a) If the owner of a new structure files the claim, the board
must receive the claim not later than one year after the date the structure was
first occupied or two years after completion, whichever comes first.
(b) If the owner of an existing structure files the claim, the
board must receive the claim not later than one year after the date the work
was substantially completed.
(c) Regardless of whether the claim involves a new or existing
structure, if the owner files the claim because the contractor failed to begin
the work, the board must receive the claim not later than one year after the
date the parties entered into the contract.
(d) Regardless of whether the claim involves a new or existing
structure, if the owner files the claim because the contractor failed to
substantially complete the work, the board must receive the claim not later
than one year after the date the contractor ceased work on the structure.
(e) If a registered contractor files the claim against a
registered contractor performing work as a subcontractor on a new structure,
the board must receive the claim not later than [one year] 14 months
after the date the structure was first occupied or two years after completion,
whichever comes first.
(f) If a registered contractor files the claim against a
registered contractor performing work as a subcontractor on an existing
structure, the board must receive the claim not later than [one year] 14 months after the work on the structure was substantially completed.
(g) If a registered contractor files the claim against a
registered contractor performing work as a subcontractor, because the
subcontractor failed to substantially complete the work, the board must receive
the claim not later than [one year] 14 months after the date the
subcontractor ceased to work on the structure.
(h) If a material or equipment supplier, an employee, or a
registered subcontractor files the claim, the board must receive the claim not
later than one year after the date the registrant incurred the indebtedness.
(4) Upon acceptance of the statement of claim, the board shall
give notice to the contractor against whom the claim is made and shall initiate
proceedings to determine the validity of the claim. If, after investigation,
the board determines that a violation of this chapter or of any rule adopted
thereunder has occurred, or damage has been caused by the registrant, the board
may recommend to the registrant such action as the board considers appropriate
to compensate the claimant. If the contractor performs accordingly, the board
shall give that fact due consideration in any subsequent disciplinary
proceeding brought by the board.
(5) Except for claims by owners of nonresidential property when
the total contract is $25,000 or less and those claims that are settled through
binding arbitration under subsection (9) of this section, any person with a
claim against a contractor involving nonresidential structures shall bring an
action upon the bond required by ORS 701.085, as provided in subsections (6) to
(8) of this section, in a court of competent jurisdiction or through binding
arbitration in compliance with ORS 36.300 to 36.365. At the option of the
claimant, a person having a claim as an owner of nonresidential property when
the total contract is $25,000 or less may elect to bring an action upon the
bond in this same manner. In such instances, all other statutes and rules
applicable to the processing of claims in accordance with subsections (5) to
(8) of this section apply.
(6) Except as set forth in subsection (5) of this section, in
order to have access to the bond required by ORS 701.085, the claimant in an
action against a contractor involving nonresidential structures must deliver a
copy of the complaint to the board and to the surety on the bond by certified
mail, return receipt requested, within 90 days of the date the complaint was
filed. The surety shall not be joined as a party to the action, but shall have
the absolute right to intervene in the action. If notice is so given, except as
provided in subsection (8) of this section, the surety that received notice
shall be bound by any judgment entered in the action, unless within 30 days of
receipt of such notice, the surety delivers to the claimant or the claimant's attorney
of record and to the board by certified mail, return receipt requested, or by
facsimile machine or form of transmission with an acknowledgement, a notice
that the surety is not the surety that should have received the claimant's
notice. If the claimant disputes the validity of the surety's notice, or if the
surety disputes the validity or timeliness of the delivery of the complaint,
the claimant may join the surety as a defendant or the surety may join as a
party in the action. If the surety elects to intervene in the action or is
joined as a party to the action, it shall be bound by all issues of fact and
law determined by the court, which issues shall not then be subject to review
by the board. The date the board receives a copy of the complaint shall be the
date the board uses to establish the priority of the claim.
(7) If a court issues a judgment against a contractor in an
action involving nonresidential structures, the claimant shall deliver a
certified copy of the judgment to the board and to the surety within 30 days of
the date of entry of the judgment in order to retain a claim against the bond.
The entry of a final judgment against the contractor shall fully and finally
conclude the contractor's involvement concerning participation in any and all
proceedings to determine whether its bond is subject to payment of the claim.
The contractor shall not be a party to the administrative process set forth in
subsection (8) of this section, which shall proceed with the claimant and
surety as the only parties.
(8)(a) Upon receipt of a timely filed copy of the judgment
specified in subsection (7) of this section, the board shall issue a proposed
order in the amount of the judgment, together with any court costs, interest
and attorney fees awarded by the court. The board's determination of the claim
shall be limited only to determinations of whether the claim comes within the
jurisdiction of the board and is subject to payment by the surety. The proposed
order shall be issued in such form as to indicate the surety's maximum
liability to the claimant. If there are no exceptions filed to the proposed
order within the time period provided therefor after issuance of the proposed
order, the proposed order shall become final without any further action required
by the board. The surety's right to except to the proposed order based upon a
judgment, except where the surety has elected to intervene in the action as set
forth in subsection (6) of this section, shall be limited to the following
issues:
(A) Whether the claim was timely filed with the board as
provided in subsection (3) of this section.
(B) Whether the surety received timely notice as provided in
subsections (6) and (7) of this section.
(C) Whether the claim is for work subject to this chapter
provided within the State of Oregon.
(D) The extent of the surety's liability to the claimant.
(b) The provisions of ORS 701.150 (4) shall in all events apply
and the surety shall be entitled to except to the proposed order as to the
specific monetary liability of the surety in connection with all claims then
pending. The surety shall not be required to pay any claim under subsection (7)
of this section until such time as it receives notice from the board under ORS
701.140 that claims are ready for payment.
(9) With the prior agreement of the claimant and registrant,
the board may resolve the claim through binding arbitration under rules adopted
by the board generally in conformance with ORS 36.300 to 36.365. The board may
also use the arbitration procedure to resolve a dispute between a person
bringing a claim and any other contractor who agrees to follow the rules of the
board.
(10) The board may require claims of less than $1,000 to be
subject to mediation or resolved through binding arbitration. Notwithstanding
the provisions of subsection (4) of this section, the board is not required to
investigate claims of less than $1,000.
(11) The board may apply the provisions of subsections (5) to
(8) of this section to any arbitration decision as it would to a judgment of a
court whether the arbitration decision is rendered by the board or by
independent arbitration.
(12) The board may delegate any of its functions described in
this section to a hearings officer. If the board delegates its authority to
decide claims to a hearings officer, the board may provide for appeal of such
orders to the board.
(13) The board by rule may require a deposit not to exceed $100
for the filing of a claim, the filing of a request for hearing or the filing of
exceptions. Such deposit is recoverable by the party.
Approved by the Governor
June 23, 1999
Filed in the office of
Secretary of State June 24, 1999
Effective date October 23,
1999
__________